Ejipura
Ejipura flyover: Contractor blames BBMP for construction delays
The firm also criticised the BBMP for releasing only 75 per cent of the mobilisation funds needed to commence the work.
29 May 2024, 19:43 IST
Ejipura flyover: Contractor blames BBMP for construction delays
29 May 2024, 19:43 IST
BBMP issues notice to contractor for slow progress in Ejipura flyover construction
The BBMP has threatened to take action as per the contract terms, including imposing liquidated damages if the company does not address the mentioned issues within seven days.
29 May 2024, 00:43 IST
BBMP issues notice to contractor for slow progress in Ejipura flyover construction
29 May 2024, 00:43 IST
No progress on Ejipura flyover: BBMP to issue notice to contractor
He issued the instruction after learning that the contractor — BSCPL Infrastructure Limited — had completed only 4 per cent of the work even after being given the contract about six months ago.
22 May 2024, 21:02 IST
No progress on Ejipura flyover: BBMP to issue notice to contractor
22 May 2024, 21:02 IST
Ejipura flyover at the expense of 207 trees? Asks varsity report
The report called for the immediate halt of the piecemeal destruction of the city’s greenery for individual projects, which has resulted in a reduction in the overall green cover of the city over the last few decades.
11 December 2023, 21:24 IST
Ejipura flyover at the expense of 207 trees? Asks varsity report
11 December 2023, 21:24 IST
BBMP begins preliminary works for Ejipura flyover project
The actual work is at least three months away, as the BBMP wants to test the existing girders and complete pre-construction activities.
08 November 2023, 22:50 IST
BBMP begins preliminary works for Ejipura flyover project
08 November 2023, 22:50 IST
Ejipura flyover fiasco: Govt seeks action against engineers involved
Besides seeking the kind of disciplinary action taken against engineers, the Urban Development Department (UDD), in its letter to BBMP Chief Commissioner Tushar Girinath, has also asked the civic body about the financial losses incurred due to the unfinished project.
07 September 2023, 04:03 IST
Ejipura flyover fiasco: Govt seeks action against engineers involved
07 September 2023, 04:03 IST
B'luru: Decision on ₹178 cr for Ejipura flyover
The civic body floated the fourth tender to revive the unfinished project, but only one bidder participated
12 June 2023, 04:21 IST
B'luru: Decision on ₹178 cr for Ejipura flyover
12 June 2023, 04:21 IST
Suggestions to make Ejipura flyover into a tramway
Can the half-done Ejipura flyover be repurposed to facilitate a much-longer tram project that can carry more people?
02 April 2023, 21:26 IST
Suggestions to make Ejipura flyover into a tramway
02 April 2023, 21:26 IST
BBMP floats 4th tender to complete Ejipura flyover
As per the new tender, the remaining work is estimated at Rs 143.80 crore
02 March 2023, 21:50 IST
BBMP floats 4th tender to complete Ejipura flyover
02 March 2023, 21:50 IST
Ejipura EWS project a single entity, state tells HC
The court is hearing a fresh PIL by the Karnataka EWS 1512 Residential Social Welfare Association, Bengaluru, alleging delay in execution of works
18 January 2023, 23:00 IST
Ejipura EWS project a single entity, state tells HC
18 January 2023, 23:00 IST
<
1